Night work ahead of schedule

Due to the good weather, night surfacing works have progressed well and there are some changes to the original dates:

Kings junction surfacing will now finish on Friday morning.

Westham Crossroads remedial work will be brought forward to between 7pm and 6am on:

  • Friday 17 June
  • Monday 20 June

King Street will then be closed between 6.30pm and midnight on (unchanged):

  • Tuesday 21 June to Friday 24 June
  • Monday 27 June

Radipole Park Drive will be closed from Jubilee Retail Park to Kings junction between 7pm and 6am on (unchanged):

  • Tuesday 28 June to Friday 1 July

Harbour Crossroads remedial work will be brought forward by two days to Monday 4 July.

Final surfacing of the centre of Kings junction will take place on Tuesday 5 July.

 

Advertisements

Tags: , ,

2 Responses to “Night work ahead of schedule”

  1. Richard Says:

    It was great last night came into town no yellow signs thru greenhill came down king street all going fine, when I got to the junction there was the first sign to tell me swannery bridge was closed. Cheers!

  2. Weymouth Transport Package Says:

    Hi Richard,

    Apologies for this oversight regarding the signage.

    The night work on Westham Crossroads is now finished. Work will now start on King Street, which will be closed between 6.30pm and midnight.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: