The roundabout and old traffic islands have been removed and work to create the new junction shape is underway.
There are two retaining walls being built, either side of Swannery Bridge, so that the road can be widened in this area.
The wall on the car park side of the bridge has been finished and this week work has started on the second retaining wall, opposite Swannery Court.
The new kerb realignment on Commercial Road is going well and has now switched sides and is moving towards the corner of King Street.
The large island on the King Street arm of the junction is also starting to be built.