Slip lanes

Westham Junction night work (large version)

Night work on Westham Junction has gone to plan with 1000 tonnes of material laid over the three nights.

This has built the level of the road up to binder level (middle road layer). Work will now start on the signal loop boxes and Siemens will soon be working in the area to put in the signals.

All the dedicated slip lanes are complete and many people will have already used the new left turn slip lane from Weymouth Way onto Swannery Bridge.

The use of the slip lanes will be limited until all associated works are finished, however, they will be open whenever possible to help the flow of traffic in the area.

Advertisements

Tags: ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: