Harbour Junction

Harbour Junction traffic managment layout (large version)

Work to build a retaining wall at Harbour Junction on the corner of Newstead Road and Boot Hill starts this week. This wall will allow the road to be widened at the junction to Boot Hill.

The piling works to build the retaining wall are contained within the works area, however during these works there will be pavement restrictions in place. The diverted pedestrian route is shown in green on the drawing above.

The works are due to last nine weeks.